When looking at a Program Board, what does it mean when a feature is placed in a team’s swim lane with no strings?

OPTIONS

  • That the feature can be completed independent from the other teams
  • That all the risks have been ROAMed
  • That the team has little confidence it will happen
  • That the feature should be completed before any other feature

Answer:

That the feature can be completed independent from the other teams

Explanation:

When a feature is placed in a team’s swim lane with no strings attached, it means that the team has the autonomy to complete the feature independently from the other teams. This means that the team does not have to wait for any other teams to complete their work before they can start working on the feature.

Swim lanes are a common tool used in Agile development to represent the work of different teams. Each swim lane is assigned to a specific team, and the cards in the swim lane represent the features or tasks that the team is responsible for delivering.

When a feature is placed in a team’s swim lane with no strings attached, it means that the team has the ability to start working on the feature immediately, without having to wait for any other teams to complete their work. This can help to improve the efficiency and speed of the project, as the team can focus on delivering the feature without being held up by other teams.

In summary, when a feature is placed in a team’s swim lane with no strings attached, it means that the team has the autonomy to complete the feature independently from the other teams, improving the efficiency and speed of the project.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version