What is one of the Agile Release Train sync meetings?

OPTIONS

  • Solution Demo
  • Scrum of scrums
  • Iteration Retrospective
  • Iteration Review

Answer:

Scrum of scrums

Explanation:

Scrum of Scrums is one of the Agile Release Train (ART) sync meetings that is used in large-scale Agile projects. The purpose of the Scrum of Scrums is to provide a forum for cross-team communication and coordination, ensuring that the different teams are aligned and working towards the same goals.

In Scrum of Scrums, representatives from each team meet regularly to discuss cross-team dependencies, challenges, and progress. The representatives are usually the Scrum Masters or key members of the development team, and they act as the “voice” of their respective teams.

During the Scrum of Scrums, the representatives discuss any issues that are affecting multiple teams and work together to find solutions. They also provide updates on the progress of their teams, ensuring that the other teams are aware of any changes that may impact their work.

The Scrum of Scrums is an important component of the ART sync meetings, as it helps to ensure that the different teams are aligned and working together effectively. This helps to reduce the risk of delays and increase the chances of delivering the project on time and within budget.

In conclusion, Scrum of Scrums is one of the Agile Release Train sync meetings that is used to provide a forum for cross-team communication and coordination, ensuring that the different teams are aligned and working towards the same goals.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version