What are two of the Agile Release Train Sync meetings? (Choose two.)

OPTIONS

  • Product Owner Sync
  • System Demo
  • Solution Demo
  • Scrum of Scrums
  • Inspect and Adapt

Answer:

  • Product Owner Sync
  • Scrum of Scrums

Explanation:

The two Agile Release Train (ART) sync meetings are the Product Owner (PO) Sync and the Scrum of Scrums (SoS).

The PO Sync meeting is a regular meeting that is attended by the product owners from each Agile team within the ART. The purpose of this meeting is to align the product backlogs and to ensure that the ART is working towards a common goal. The PO Sync meeting is an opportunity for product owners to share updates, ask questions, and resolve any cross-team dependencies.

The Scrum of Scrums (SoS) is another important ART sync meeting. It is attended by the Scrum Masters from each Agile team within the ART. The purpose of this meeting is to coordinate the work of the various Agile teams and to address any cross-team dependencies. The Scrum Masters use this meeting to share information about the progress of their respective teams and to identify and resolve any obstacles that may be blocking the teams from delivering value to the end-users.

In summary, the PO Sync and SoS meetings play a crucial role in ensuring that the ART is aligned and working effectively towards a common goal.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version