If 20 men can construct a divider of 112 meters in length in 6 days, what length of a comparable divider can be worked by 25 men in 3 days?

OPTIONS

  • 69 meters.
  • 58 meters.
  • 70 meters.
  • 76 meters.

70 meters.

Explanation:

 Length of a comparable divider can be worked by 25 men in 3 days=X

X = (Length of divider built by 25 men in 6 days)*(25 men/20 Men)*(3 days/6days)
X = (112)*(25/20)*(3/6)
X= 70

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version