Home » 2021 (Page 40)

Find what is the EPEI?

If Actual Setup time is 100 minutes and Total Available setup time provided by the model is 200 minutes and you have a total of 10 machines, what is the EPEI? OPTIONS 5 days 10 days 20 days Data not enough ANSWER 5 DAYS EXPLANATION...
Read More

FIND THE TAKT TIME.

If the customer demand for a product is 100 products, total time is 480 minutes out of which 30 minutes lost to setup and 60 minutes for meetings, what is the TAKT Time? OPTIONS 3.9 minutes per product 3.6 minutes per product 4.2 minutes per...
Read More

The basic benefit of implementing Lean is to

OPTIONS Improve productivity Improve quality Achieve Continuous Flow in the product Reduce Inventory ANSWER Achieve Continuous Flow in the product EXPLANATION The main benefit of implementing Lean is to bring about continuous flow in the product. All other benefits come as a by-benefit.
Read More

Which of the below projects moves towards a quick win?

OPTIONS Lean TRIZ Six Sigma Kaizen Blitz ANSWER Kaizen Blitz EXPLANATION Lean, Six Sigma and sometimes TRIZ as well turn out as gradual improvement approaches. Kaizen Blitz is considered a fast approach in terms of how quickly results are achieved. Thus Kaizen Blitz is correct.
Read More