If Actual Setup time is 100 minutes and Total Available setup time provided by the model is 200 minutes and you have a total of 10 machines, what is the EPEI?

OPTIONS

  • 5 days
  • 10 days
  • 20 days
  • Data not enough

ANSWER

5 DAYS

EXPLANATION

EPEI = 100 mins/200 mins = 0.5. 10 machines will have to be changed over, thus the EPEI is 5 days.