If the customer demand for a product is 100 products, total time is 480 minutes out of which 30 minutes lost to setup and 60 minutes for meetings, what is the TAKT Time?

OPTIONS

  • 3.9 minutes per product
  • 3.6 minutes per product
  • 4.2 minutes per product
  • 5.9 minutes per product
  • 4.8 minutes per product

ANWER

R3.9 minutes per product

EXPLANATION

By applying standard TAKT Time formula (T=Ta/D)

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version