An improvement project failed to create the expected value because the team did not spend enough time thinking about how successful the solution would be. What would have helped to prevent this failure?

OPTIONS

  • Kanban
  • Risk management
  • Measurement and reporting
  • Cascading objectives

ANSWER

Risk management

EXPLANATION

If risks are not properly understood, teams could be directed to undertake projects that are certain to fail. If team members notice risks but do not see evidence of preventative actions, they may lose confidence in their project, thereby increasing the likelihood of failure.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version