Which statement about a change authority is correct?

OPTIONS

  • A single change authority should be assigned to authorize all types of change and change models
  • A change authority should be assigned for each type of change and change model
  • Normal changes are pre-authorized and do not need a change authority
  • Emergency changes can be implemented without authorization from a change authority

Answer:

A change authority should be assigned for each type of change and change model

Explanation:

It is essential that the correct change authority is assigned to each type of change to ensure that change enablement is both efficient and effective. For normal changes, change models based on the type of change determine the roles for assessment and authorization.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version