Home » Certification Exams Questions » ITIL v4: When should a full risk assessment and authorization be carried out for a standard change?

OPTIONS

  • Each time the standard change is implemented
  • When the procedure for the standard change is created
  • At least once a year
  • When an emergency change is requested

Answer:

When the procedure for the standard change is created

Explanation:

A full risk assessment does not need to be repeated each time the standard change is implemented. It only needs to be done if there is a modification to the way it is carried out.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version