Home » Certification Exams Questions » If Cp = 1.3, Cpk = 1.2, what should the Black Belt do first?

OPTIONS

  • Leave the process to chance variations
  • Identify signal and keep looking out for signals
  • Center the mean
  • None of the above

Correct Option:A

Leave the process to chance variations

EXPLANATION

A Black Belt doesn’t have to work on this process at all, as the process is capable and the mean is centered as well, so THE FIRST OPTION is correct.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version