Home » Certification Exams Questions » If Cp = 1.2 Cpk = 0.7, what should the Black Belt do first?

OPTIONS

  • Reduce variations
  • Center the mean
  • Bring the process in statistical control
  • The choice of what to do rests with the Black Belt

ANSWER

Center the mean

EXPLANATION

As the difference between Cp and Cpk is relatively large, the Black Belt should look to center the mean.