Answer:

Product Owner, Development Team, and other involved parties

Explanation:

In order to confirm that the events and artifacts are transparent, The Scrum Master must work in close association with the Product Owner, Development Team, and other involved parties. It is also the responsibility of the The Scrum Master to take appropriate steps if any discrepancies with regards to the process is found out.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version