Home » Certification Exams Questions » CSM - Certified Scrum Master » Who collaborates and understands the work of the Sprint?

OPTIONS

a. The Scrum Team
b. The Scrum Master and the Development Team
c. The Product Owner and the Development Team
d. The Development Team

Answer:

The Scrum Team

Explanation:

Each entity of the Scrum Team works in close association to understand the working of the Sprint. While the Development Team works to create functionality that will be developed during the Sprint, the Product Owner discusses the objective that the Sprint should achieve and the Product Backlog items that should be completed in the Sprint, to achieve the Sprint Goal.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version