An IT manager is planning improvements. They have identified four stakeholders and how they will be affected by the improvement. Which two stakeholder groups have high impact and high involvement?

1. Customers, who will see improved value from the services
2. IT director, who will provide funding and will see significant efficiency improvements
3. Team members, who will change how they work and contribute to design of updated processes
4. Other IT teams, who may need to work with updated processes

OPTIONS

  • 1 and 2
  • 2 and 3
  • 3 and 4
  • 1 and 4

ANSWER

2 and 3

EXPLANATION

(2) The IT director will provide funding, which means they will have a high impact on the improvements. They also need to see efficiency improvements, so they have high involvement. Stakeholders with high impact and high involvement should be fully engaged with the initiative and satisfied with the improvement. (3) Team members need to contribute to design of updated processes, so they will have a high impact on the improvements. They also need to change how they work, which means they have a high involvement. Stakeholders with high impact and high involvement should be fully engaged with the initiative and satisfied with the improvement.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version