Home » Certification Exams Questions » CSM - Certified Scrum Master » Which one is the true for Sprint Planning?

OPTIONS

  • The work to be performed in the Sprint is planned
  • Demo of the previous increment is done
  • Customers will share the feedback
  • The Product Backlog is refined

Answer:

The work to be performed in the Sprint is planned

Explanation:

Sprint planning is all about determining product backlog items on which the team will work during that sprint. It is an event in the Scrum framework.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version