An organization recently completed a major system implementation that is a part of a wider modernization effort. Although the implementation was completed, there were many challenges and issues. Which approach can best help future implementation projects to be more successful?

OPTIONS

  • Use new team members for each project to ensure failures are not repeated
  • Increase funding for future initiatives so the team has more money to deal with unexpected issues
  • Document and communicate lessons learned to avoid the same mistakes in the future
  • Automate future implementations as much as possible to avoid human errors

ANSWER

Document and communicate lessons learned to avoid the same mistakes in the future

EXPLANATION

If the expected results of the improvement were not achieved or were achieved in a way different from planned, the initiative should be reviewed, and stakeholders need to be informed of the reasons for the failure of the initiative. This requires a thorough analysis of the improvement initiative, documenting and communicating the lessons learned. It should include a description of what can be done differently in the next iteration, based on the experience gathered.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version