The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?
The analyzing step of the Portfolio Kanban system has a new Epic with a completed Lean business case. What best describes the next step for the Epic?
OPTIONS
- It will be moved to the Portfolio Backlog if it receives a ‘go’ decision from Lean Portfolio Management
- It will be implemented if it has the highest weighted shortest job first (WSJF) ranking
- It will remain in the analyzing step until one or more Agile Release Trains have the capacity to implement it
- It will be implemented once the Lean business case is approved by the Epic Owner
Answer:
It will be moved to the Portfolio Backlog if it receives a ‘go’ decision from Lean Portfolio Management
Explanation:
The “go” decision from Lean Portfolio Management refers to the decision-making process for determining which epics should be developed next and which should be deferred or cancelled. This decision is based on the completion of a business case for each epic, which outlines the benefits, costs, and risks associated with the work. If an epic receives a “go” decision, it means that the Lean Portfolio Management team has evaluated the business case and determined that the epic should be moved to the Portfolio Backlog for further development.