Home » Certification Exams Questions » Process conditions are given below: USL = 32, LSL = 29, Target = 30.5, Process Mean = 31.8. A Black Belt’s comment on such a process after all investigating all pre conditions is

OPTIONS

  • The process is stable
  • The process seems to be capable on specification
  • The process is capable on target
  • The process could be unstable, and the degree of confidence on future stability is low

ANSWER

The process could be unstable, and the degree of confidence on future stability is low

EXPLANATION

The process mean within the USL states process stability although Control limits may still be less, it could be fair in saying the process could be unstable, and the degree of confidence on future stability is low.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version