Home » Certification Exams Questions » CSM - Certified Scrum Master » How often are Sprint Reviews conducted or held?

OPTIONS

Once at the end of every sprint
One in the middle and one at the end of every sprint
One at the beginning of the sprint
Daily

Answer:

Once at the end of every sprint

Explanation:

At the end of each sprint, the team is expected to deliver a potentially shippable product increment (a coded, tested, and usable piece of software). A sprint review meeting is held after each sprint in order to evaluate the increment.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version