Project managers are constantly having to compete for and reallocate specialist staff. As a result, the specialists’ priorities are constantly changing and they are frequently required to delay work on one task in order to complete a task that has been given a higher priority. How do these constantly changing priorities affect the organization’s performance measures?

OPTIONS

  • Increased throughput
  • Reduced work item age
  • Increased work in progress
  • Reduced wait time

ANSWER

Increased work in progress

EXPLANATION

Work in progress (WIP) is a measure of unfinished work items. Delaying tasks and starting other tasks increases the WIP queue.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version