At the end of PI Planning after dependencies are resolved and risks are addressed, a confidence vote is taken. What is the default method used to vote?

OPTIONS

  • A vote by team then a vote of every person for the train
  • A vote by every person then normalized for the train
  • A vote by team normalized for the train
  • A single vote by every person for the train

Answer:

A single vote by every person for the train

Explanation:

“Vote of confidence” is a term commonly used in the context of PI (Program Increment) Planning in SAFe (Scaled Agile Framework) for Lean software development.

During PI Planning, the Vote of Confidence is a moment where the team members and stakeholders express their confidence in the plan for the upcoming Program Increment (PI). This vote is typically taken at the end of the PI Planning event, and serves as a measure of the team’s agreement and commitment to the plan.

The Vote of Confidence is seen as a critical step in the planning process, as it helps to ensure that everyone is aligned on the goals and objectives for the upcoming PI, and that all team members and stakeholders understand their roles and responsibilities. It also provides a clear signal to upper management and stakeholders that the team is fully committed to executing the plan and delivering value to the customer.

In practice, the Vote of Confidence is usually a verbal or written expression of agreement and commitment, often involving the team members raising their hands or indicating their agreement in some other way. The goal is to ensure that everyone is on the same page and fully committed to the plan before moving forward with execution.

Leave a Reply

Your email address will not be published. Required fields are marked *

*
*

Latest

You need someone on your team who will work across value streams and programs to help provide the strategic technical direction that can optimize portfolio outcomes. What portfolio-level must you fill?
Who is responsible for managing the Portfolio Kanban?
What portfolio-level role takes responsibility for coordinating portfolio Epics through the Portfolio Kanban system?
Which role accepts Capabilities as complete?
Who is responsible for the Solution Backlog?
Exit mobile version