ITIL v4: When should a full risk assessment and authorization be carried out for a standard change?
OPTIONS
- Each time the standard change is implemented
- When the procedure for the standard change is created
- At least once a year
- When an emergency change is requested
Answer:
When the procedure for the standard change is created
Explanation:
A full risk assessment does not need to be repeated each time the standard change is implemented. It only needs to be done if there is a modification to the way it is carried out.