Home » Certification Exams Questions » CSM - Certified Scrum Master » Who can execute the work of the Sprint backlog?

Answer: Development Team

Explanation:

Development Team is responsible for creating The Sprint Backlog, a forecast that explains the functionality required for next Increment. The Sprint Backlog is the set of Product Backlog items selected for the Sprint, along with a plan for delivering the product Increment while realizing the Sprint Goal. The Sprint Backlog also specifies the work needed to be done in order to deliver the functionality into a “Done” Increment.