Home » Certification Exams Questions » Which of the following activities is a value-added activity?

OPTIONS

  • Testing and Inspection
  • Setup
  • Process
  • Storage

ANSWER

Process

EXPLANATION

Any time and effort spent on testing, inspection, storage, and setup is a non-value added activity. The only activity that is adding any value to the product is process.