Home » Certification Exams Questions » CSM - Certified Scrum Master » What is the recommended size for a Development Team (within the Scrum Team)?

Answer: 3-9

Explanation

The Scrum Guide suggests having between three and nine team members who are actually executing the sprint backlog. That means you wouldn’t include the product owner or scrum master in the total unless either of them is implementing the sprint backlog items.