Home » Certification Exams Questions » LSSGB: To simplify the planning and scheduling of large and complex projects, which of the project management tools should be used by the Six Sigma team?

OPTIONS

  • Work Breakdown Structures
  • Gantt Chart
  • Arrow Diagram
  • PERT

ANSWER

PERT

EXPLANATION

Though Gantt Chart is typically used as a scheduling tool, usage of PERT is synonymous with scheduling of complex projects.