If Cp = 0.8. Cpk = 0.7, what should the Black Belt do first?
ANSWER
- Reduce variations
- Center the mean
- Bring the process in statistical control
- The choice of what to do rests with the Black Belt
ANSWER
Reduce variations
EXPLANATION
Cp value less than 1 automatically indicates that variations are high in the process