For Attribute Data, what is the typical flow of events with respect to the two activities, Baselining and Measurement system analysis?
OPTIONS
- Baseline then do MSA
- MSA then do Baseline
- Baseline then do MSA then do re-MSA
- No specific flow as such and depends on the decision of the Black Belt
ANSWER
Baseline then do MSA then do re-MSA
EXPLANATION
Baselining should always be done twice – Once before MSA and once after MSA. This also shows improvement done by fixing Measurement System Variation.