Which of these doesn’t symbolize a traditional organization?

OPTIONS Planning is often short term Decisions are often taken unilateral Performance measures depend on if the customer is satisfied or not None of the above ANSWER Performance measures depend on if the customer is satisfied or not EXPLANATION In a traditional organization, you would...
Read More

Find the Control Limits

The number of defective items counted in a batch of 250 is on an average found to be 28. The Control Limits are OPTIONS 13, 45 10, 40 9, 36 11, 44 ANSWER 13,45 EXPLANATION Using np chart calculations, the Control Limits are 13,45.
Read More

Find the Control Limits

OPTIONS 0.12, 0.270.15, 0.300.20, 0.400.22, 0.44 ANSWER 0.12, 0.27 EXPLANATION Using p chart calculations the control limits 0.12, 0.27.