Calculate the Production Cycle Efficiency of the line if value added work happens for 3 hours and the product is shipped in 5 hours from order receipt time
OPTIONS
- 0.2
- 0.4
- 0.6
- 0.8
ANSWER
0.6
EXPLANATION
Using standard formula for Production Cycle Efficiency, 0.6 is correct.