Home » Certification Exams Questions » LSSGB: A team project charter is essential for all of the following reasons, EXCEPT:

Options

  • It ensures the team champion will be supportive
  • It guides the team to focus on the appropriate problem
  • It leads to a solution that aligns with the organization’s goals
  • It provides a complete history of the project

Answer

It provides a complete history of the project

EXPLANATION

Please note that a negative response is requested. Options a, b, and c are valid reasons for a project charter. The project charter will be the initial starting point of a project and does not provide its total history. 