Which is an example of a progress measurement for the project?
An organization has a project to replace all of its desktop computers, using several support teams. Which is an example of a progress measurement for this project?
OPTIONS
- Number of desktop computers replaced without following an approved procedure
- Percentage of desktop computers replaced within the allocated task time
- Number of desktop computers replaced by each support team per month
- Percentage of desktop computers replaced and confirmed as being complete
ANSWER
Percentage of desktop computers replaced and confirmed as being complete
EXPLANATION
Progress measurements demonstrate the degree of achievement to defined milestones and/or deliverables. They may be seen as indicators of something’s degree of completeness.